StandpointKnowledge Management
Contract management decides your margin
Companies lose money after signature, not during the negotiation. Where the loss happens, and how to stop it.

A four-year supply contract, properly negotiated, signed, filed. Two years later energy prices have risen and the price adjustment clause was never invoked, because nobody owned it. Three customer change requests were performed and never charged as variations. The customer has been paying late for months, and nobody has ever claimed default interest. The contract is legally sound. The money is gone anyway.
That is not an outlier, it is ordinary business. And it is why contract management is not a piece of legal housekeeping. It is a question of margin.
The loss happens after signature
World Commerce & Contracting (WorldCC) has studied this loss for more than a decade. The 2023 report published with Deloitte puts it at an average of 8.6 percent of contract value. The best performers sit at a little over 3 percent, the weakest above 20 percent. Ten causes are named, and only two of them live in the contract text: unclear scope and a lack of flexibility. The rest are handovers, ownership, and follow-through.
A word on reliability before anyone walks into a board meeting with that number. It comes from workshops, interviews, and surveys across 1,236 organizations, collected between April 2021 and December 2022. That is self-reporting, not an audit. WorldCC says so itself about the predecessor figure of 9.2 percent, with remarkable candor.
I still consider it the most important number in contracting, though for a different reason than the one it is usually cited for. It is not a calculation base for your business. It is evidence that practitioners worldwide report the same experience: the contract is negotiated as if signature were the finish line, and after that nobody looks at it again.
One item in this field, by contrast, is no estimate at all. It can be calculated to the cent. Where a commercial customer pays late, Section 288(2) BGB gives the creditor nine percentage points above the base rate, which at a base rate of 1.52 percent (as of 1 July 2026) is 10.52 percent a year, plus a flat 40 euros per claim under Section 288(5) BGB. Six months of delay on 500,000 euros is a little over 26,000 euros. Not asking for it is not a courtesy to a good customer. It is a quantified claim given up.
11% in procurement
In January 2026 WorldCC followed up. The report “Closing the Procurement Value Gap” puts value erosion in procurement contracts at 11 percent, and this time the number is broken down. Around two to three percentage points each go to missed savings, unrecorded changes, and poorly planned renewals. One to two points each go to unmanaged clauses, untracked price adjustments, and penalties and disputes arising from missed obligations.
Two things about that, and both belong on the record. First, the report was produced with a contract software vendor, as was a September 2025 study in which 70 percent of nearly 200 companies surveyed admit to a disconnect between their contracts and their financial oversight. A company selling software has an interest in a large number. The methodology behind the 11 percent is not publicly disclosed.
Second, the breakdown is nonetheless the most useful thing this research has produced so far. Not one of those items arises while drafting. All of them arise afterwards, in performance, and all of them are manual work.
How large the loss is depends on your industry
The spread is the real finding. The same study adds the cost of contracting to the value lost and measures both against revenue. For an average consumer goods company it arrives at 2 to 4 percent of revenue. In sectors running high-value capital projects, machinery and plant engineering above all, the same figure rises above 15 percent, because there both sides negotiate, buying and selling, and both sides lose.
You cannot recalculate any of this for your own business, and that is not the point. The point is the finding behind the numbers: the more complex, the longer running, and the more heavily negotiated your contracts are, the more money you lose in performance. If you export machinery, plant, or components, you sit at the upper end of that scale, not the lower one.
| Where the loss arises | What it looks like in export business |
|---|---|
| Unclear scope | The customer expects commissioning, the price was calculated for delivery. The difference is delivered, not charged. |
| Changes without a variation order | Technical adjustments run through project management, never through the contract. In the end there is no basis for the claim. |
| Price adjustment not invoked | The clause is in the contract, the deadline for giving notice passes unused. |
| Deadlines and notices of defect | Defect claims, delay damages, and liquidated damages lapse or are time-barred because nobody monitors them. |
| An invalid clause | The liability cap falls away entirely once there is a dispute. Here you do not lose a share, you lose all of it. |
Under German law you do not lose a share, you lose the clause
The international debate about value erosion counts in percentages. German standard-terms law knows no such middle ground. An overreaching liability clause is not trimmed down to the permissible maximum, it is struck, and the statutory regime takes its place (Section 306(2) BGB). A supplier who wanted to cap liability at the order value then faces unlimited liability. That is not a proportional loss of value, that is the total failure of the most expensive clause in the contract.
It gets worse, because review between businesses is barely gentler. What is prohibited against consumers is treated as indicative of unreasonable disadvantage between businesses as well.1 How a clause has to be built to survive is set out in the article “Why your limitation of liability in B2B contracts fails”; why the popular rescue formula rescues nothing, in the article “As far as legally permissible”.
And the most frequent cause of loss in the study, unclear scope, is not a soft litigation topic under German law. It is the basis of every claim for additional payment. If you do not describe precisely what you owe, you cannot prove what you delivered beyond it. See the article “The statement of work”.
Why the gap is getting more expensive right now
Multi-year contracts are currently running through an environment they do not reflect. Tariffs change within weeks, sanctions lists grow, lead times and energy prices swing, payment terms are stretched. Every one of those movements is either covered by the contract or it is not.
If it is covered, somebody has to invoke the clause, on time and with evidence. If it is not, the statute decides, and Section 313 BGB helps less often than companies hope. Both are tasks that arise in daily business, not in the negotiation. And that is precisely where, in most companies, nobody is in charge.
On stretched payment terms the law is in fact better than practice assumes. The Court of Justice of the European Union has held that a payment period of more than 60 calendar days set unilaterally by the debtor is not an express agreement within the meaning of Article 3(5) of the Late Payment Directive, unless it can be established that both parties intended to be bound specifically by that term.2 But nobody plays that card if nobody in the company holds incoming payments against the contract.
A WorldCC survey from June 2026 shows this against the geopolitical backdrop. 39 percent of the companies surveyed have no formal process for geopolitical risk or only an ad hoc arrangement, 15 percent have board-level oversight with defined escalation triggers. 35 percent made no clause changes at all over twelve months. Where changes were made, they almost always concerned price escalation and force majeure. The survey states no sample size; it works as a mood reading, not as a statistic.
The finding behind it is the interesting one, and it fits everything above: the problem is worked on at clause level, not at the level where it arises. Buyers protect themselves with long-term fixed prices, sellers with escalation clauses. So both sides negotiate over who carries a disruption that neither of them caused. And because nobody steers this in daily business, the outcome gets renegotiated rather than claimed: almost two thirds of affected cases end in a renegotiation, not in a claim.
Two invoices from practice
A mid-sized company once assured me that its contracts had never caused any problems. That is never true. Shortly afterwards, its in-house lawyer pointed me to a maintenance contract that renewed automatically every year unless somebody terminated it in time. The fee was 70,000 euros a year. The plant it covered had been standing idle for years. Nothing was maintained, and payment continued. By the time anyone noticed, the maintenance provider was insolvent and the claim for repayment was worthless in practice.
One contract, 70,000 euros a year, over several years. Any contract management at all, however plain, would have found that item in its first pass. Anyone who considers such a system too expensive should put that number next to it.
The other side of the ledger I know first-hand from a senior in-house counsel at a DAX-listed group. There, supply contract monitoring is automated. On the first day of delay, a letter goes out to the supplier automatically, with the liquidated damages agreed in the contract. No discretion, no discussion, nothing forgotten. That company has grasped what most legal departments do not even claim for themselves: law does not only cost money, it can earn it.
Why the loss stays invisible
How widespread this is shows in the 2025 CCM Benchmark, which WorldCC publishes together with a software vendor. 88 percent of the organizations surveyed recognize that contract and commercial management directly affects the resilience of the business. At the same time, 70 to 80 percent of them lack clear accountability for contracting performance. Recognition without ownership, that is the whole finding in two numbers.
Two patterns explain why it stays that way.
The first is split ownership. A contract touches procurement, sales, engineering, project delivery, and legal. Each of those functions owns a slice, none owns the outcome. Whoever should invoke the price adjustment takes it for a sales task, sales takes it for a procurement task, procurement takes it for a legal one. Everyone has seen the contract, nobody invokes the deadline. The figure above is nothing but that condition, measured in percent, and the countermeasure is not bureaucracy but a name on the cover sheet.
The second is the normalization of deviance. The term comes from risk research; the sociologist Diane Vaughan coined it in her study of the Challenger disaster. A deviation from the standard passes without consequence, becomes a habit, and eventually becomes the standard itself. The first variation order that goes unwritten costs nothing. The tenth is company practice, and at some point nobody asks any more why project margins always come in thinner than calculated.
Some run a briefing, almost nobody runs a debriefing
Well-prepared companies enter a negotiation with a briefing. Objectives, limits, roles, fallback positions, ideally in writing. Far from everyone does that, and after signature almost nobody does anything at all. Hardly any company sits down once the project is finished and asks which clause caused trouble in performance, which concession turned out expensive, which deadline nobody had on the radar, and what the other side did better.
The consequence is expensive and quiet at the same time. The knowledge stays in the heads of the people involved, leaves the project with them and eventually leaves the company. The next negotiation starts from zero, and the same mistake costs the same money a second time.
A debriefing takes two hours and belongs in knowledge management, not in an inbox: one page per project, linked to the clause at issue, findable by whoever negotiates the same contract two years from now. It is the cheapest part of contract management and the only one that improves with every round.
Lawyers alone cannot prevent the loss
The decisions that cost money are rarely made by the lawyers. The buyer who accepts the other side’s standard terms without objection. The salesperson who makes a commitment by email. The project manager who performs a change without writing the variation order.
So the answer to value erosion is not a thicker contract, and it is not software either. It is enabling the people who apply the contract every day, plus a short, rehearsed process.
Contract management does not start with software
The reflex runs the other way. Value erosion identified, so a system is procured, ideally one with artificial intelligence in it. I recommend the reverse order, and I do not sell software.
The first step is an inventory: which contracts are running, who owns each of them, what dates they contain, and which clauses somebody has to invoke actively. That is business process work, not IT. It fits into a spreadsheet and a shared calendar and is done in a few weeks. Only then can you see where it jams, and only then is the question of tooling worth asking.
Software automates an existing process. Where none exists, it only speeds up the disorder, at a license fee. Even at the DAX-listed group, automation was the last step, not the first. Before it, somebody had to decide that day one of the delay is the trigger and that the liquidated damages are claimed without discretion.
What that sequence looks like inside a large group is now on the record. The legal department of Siemens Energy spent roughly six months first understanding how the department works and which problems had to be fixed before any digitalization. Starting from the technology, the authors hold, is unlikely to succeed: where the underlying practices are poor, digitalization magnifies the flaw instead of curing it. One of the first tools they built was, of all things, one that drafts claim letters in seconds and supplies the associated deadlines.3
One honest objection remains: part of the loss cannot be avoided. The contract is signed, then circumstances change, and no contract management in the world stops a war, an embargo, or a supplier insolvency. The monitoring itself costs working time too. So the point is not zero. The point is the distance between a little over 3 and more than 20 percent, and that distance is not a matter of luck.
Häufige Fragen
Where does contract value erosion actually happen?
Mostly after signature. Variations are performed but never charged, price adjustment clauses are never invoked, notice periods expire, and work is delivered that nobody bills. The negotiation is the visible part; the money is lost in operations.
How large is the loss, and how reliable is the number?
World Commerce & Contracting (WorldCC) and Deloitte put the 2023 average at 8.6 percent of contract value, with the best performers at a little over 3 percent and the weakest above 20 percent. The figure rests on self-reporting by 1,236 organizations, not on audited accounts. It does not prove an exact percentage, but it does establish the order of magnitude and the spread.
What actually stops the loss?
Contract management, and first as a process, not as software: a named owner for every contract, all deadlines in the same calendar as the delivery dates, no change performed without a written basis, reviewed clauses, and training for the people who decide in daily business. Software automates an existing process; where there is none, it only speeds up the disorder.
Is this a matter for the legal department?
Only in part. The clauses come from law, the losses arise in procurement, sales, and project delivery. Stopping the loss means enabling the people who decide about the contract in daily business.
Notes
-
BGH, judgment of 19 September 2007 – VIII ZR 141/06. ↩
-
CJEU, judgment of 6 February 2025 – C-677/22. In that case the debtor had, in conditions it drew up alone, set a payment period of 120 calendar days. ↩
-
Inga Ponnath/Florian Koemm, The (Rocky) Road – A Digitalization Example From Siemens Energy’s Legal & Compliance Team, RInPrax 2025, 128. ↩
Reference: Poleacov, P. (2026). Contract management decides your margin. INN.LAW. https://inn.law/en/perspectives/contract-management-value-erosion/